Quick answer
- A single-car driveway, 10 × 50 ft, at 4 inches deep: about 6.2 cubic yards, about 8.6 tons of crushed stone — before any compaction or waste allowance.
- A double driveway, 20 × 40 ft, at 4 inches: about 9.9 cubic yards, about 13.8 tons.
- A long single driveway, 12 × 100 ft, at 4 inches: about 14.8 cubic yards, about 20.7 tons.
- One ton covers about 116 sq ft at 2 inches deep, about 58 sq ft at 4 inches, and about 39 sq ft at 6 inches — for crushed stone at 1.4 tons per cubic yard (see the note on density below).
- A new driveway is not one layer. Build it as a 4–6 inch compacted base plus a 2–3 inch top layer, and order 15–25% extra for compaction on the layers you compact — the raw table numbers are the finished, compacted volume, not the loose order.
How the numbers are worked out
Cubic yards = length (ft) × width (ft) × depth (inches) ÷ 324.
Tons = cubic yards × 1.4 (crushed stone, the figure used through this guide).
The 324 is 27 (cubic feet in a cubic yard) × 12 (inches in a foot). Worked example — a 12 × 50 ft driveway at 4 inches:
- Area = 12 × 50 = 600 sq ft.
- Cubic yards = 600 × 4 ÷ 324 = 7.41 yd³.
- Tons = 7.41 × 1.4 = 10.37 tons.
Tons and yards by driveway size
Single-layer figures at the finished depth shown, before compaction/waste allowance. Add 10% for a top-up on an existing driveway, 15–25% for a new compacted base (see below).
| Driveway size | Area | 4 in deep — yd³ / tons | 6 in deep — yd³ / tons |
|---|---|---|---|
| 10 × 20 ft (parking pad) | 200 sq ft | 2.47 / 3.5 | 3.70 / 5.2 |
| 12 × 40 ft | 480 sq ft | 5.93 / 8.3 | 8.89 / 12.4 |
| 10 × 50 ft (single-car) | 500 sq ft | 6.17 / 8.6 | 9.26 / 13.0 |
| 12 × 50 ft | 600 sq ft | 7.41 / 10.4 | 11.11 / 15.6 |
| 20 × 40 ft (double) | 800 sq ft | 9.88 / 13.8 | 14.81 / 20.7 |
| 12 × 100 ft (long single) | 1,200 sq ft | 14.81 / 20.7 | 22.22 / 31.1 |
How far a ton goes
| Depth | 1 ton covers | 1 cubic yard covers |
|---|---|---|
| 2 in | ~116 sq ft | ~162 sq ft |
| 3 in | ~77 sq ft | ~108 sq ft |
| 4 in | ~58 sq ft | ~81 sq ft |
| 6 in | ~39 sq ft | ~54 sq ft |
A note on the round numbers you will see elsewhere: many guides say “about 100 sq ft per ton at 2 inches” and “about 50 sq ft at 4 inches”. Those use a heavier density (about 1.6 tons per cubic yard) or are rounded down for safety. This guide uses 1.4 tons per cubic yard throughout, so its coverage figures are slightly higher; if your supplier quotes a heavier stone, use their tons-per-yard figure instead — the cubic-yard column does not change.
How deep should a gravel driveway be?
- Top-up on an existing driveway: 1–2 inches of fresh top stone.
- Top layer on a new driveway: 2–3 inches.
- New driveway, total build-up: 4–6 inches of base plus 2–3 inches on top — 6–9 inches in total, built in layers, each compacted.
- Heavy vehicles (RVs, work trucks): go to the deep end of the base range and use crusher run for the base, which locks together under compaction.
Depth is finished, compacted depth. Gravel delivered loose settles when compacted, which is why the order needs the allowance below.
Build it in layers — a worked example
A 12 × 50 ft new driveway (600 sq ft), 4-inch base + 2-inch top:
| Layer | Material | Depth | Cubic yards | Tons |
|---|---|---|---|---|
| Base | Crusher run / dense-graded (1.55 tons/yd³) | 4 in | 7.41 | 11.5 |
| Top | #57 clean stone (1.35 tons/yd³) | 2 in | 3.70 | 5.0 |
| Raw total | 6 in | 11.11 | 16.5 | |
| Order, with ~20% compaction allowance | ~20 tons |
Which gravel, and how heavy is it?
| Material | Tons per cubic yard | Best use |
|---|---|---|
| Pea gravel | 1.30 | Paths, decorative areas — not driveways; it rolls under tyres |
| #57 clean angular stone | 1.35 | Driveway top layer, drainage |
| Crushed stone, general | 1.40 | All-round driveway stone |
| Crusher run / dense-graded | 1.55 | Base layer — fines lock together when compacted |
| River rock / decorative stone | 1.28 | Landscaping, not driveways |
Pea gravel and river rock look good in a garden bed and fail on a driveway: round stone does not interlock, so tyres push it aside and ruts form. Angular crushed stone locks together — that is the whole point of a driveway surface.
The two allowances people forget
- Compaction: add 15–25%. Dense-graded base material tightens to roughly 85–95% of its loose volume when compacted. On the worked example above, 16.5 tons of raw volume becomes about 20 tons to order.
- Waste and spreading: add 10%. Edges spread wider than measured — if you want 12 feet of usable surface, calculate on 14 feet — plus spillage and uneven ground. On a flat, square top-up, 10% is enough; on a slope or irregular shape, go higher.
The two allowances stack on a compacted layer: ordering 25–30% above the raw calculated volume for a new driveway base is normal, not padding. Do not add the compaction allowance twice — once, on the total order, is the rule.
Bags vs bulk
Bulk by the ton is the only sensible way to buy driveway gravel. For scale: one cubic yard is about 45 bags of 80 lb concrete-mix size, and gravel bags are sold by weight in the same way — a 1-ton order is roughly 40 × 50 lb bags. Past a cubic yard or so, bulk delivery is cheaper per ton and far less handling. Use the gravel calculator for your exact size, then ask the supplier for the price per ton delivered, not per yard — bulk gravel is priced by weight. For context on what to expect, see how construction material prices have risen since 2020.
Common mistakes
- Ordering the finished volume, not the loose volume. The table gives compacted volume. A new base needs 15–25% more stone delivered than the table says.
- One layer, 4 inches, done. A single 4-inch layer on bare soil ruts and washes out. Base plus top, each compacted, is what lasts.
- Pea gravel on a driveway. Round stone rolls; angular stone locks. The wrong shape undoes the right depth.
- Measuring the width you want, not the width you will get. Edges spread — measure 2 feet wider than the finished surface.
- Skipping the base on soft ground. On clay or soft soil, a geotextile fabric under the base stops the stone sinking into the mud. Thickness cannot compensate for a base that disappears.
FAQ
How much gravel do I need for a driveway?
Measure length × width × depth, divide by 324 for cubic yards, multiply by 1.4 for tons. A 10 × 50 ft single-car driveway at 4 inches is about 6.2 cubic yards / 8.6 tons before allowances; a new driveway needs 15–25% more for compaction.
How many tons of gravel for a 12 × 40 ft driveway?
About 8.3 tons at 4 inches deep, about 12.4 tons at 6 inches — raw volume, before the compaction allowance on a new build.
What area will 1 ton of gravel cover?
About 116 sq ft at 2 inches deep, about 58 sq ft at 4 inches, for crushed stone at 1.4 tons per cubic yard. Heavier stone covers less per ton.
How deep should a gravel driveway be?
4–6 inches of base plus 2–3 inches on top for a new driveway; 1–2 inches for a top-up on an existing one.
How many yards of gravel in a ton?
About 0.71 cubic yards per ton at 1.4 tons per cubic yard (1 ÷ 1.4). Pea gravel is about 0.77 yd³ per ton; crusher run about 0.65 yd³ per ton.
Pea gravel vs crusher run for a driveway?
Crusher run for the base — it locks under compaction. Pea gravel is for paths and decoration; it rolls under tyres and ruts on a driveway.
Ready to estimate? Enter your driveway size and depth in the gravel calculator for cubic yards and tons, with waste and compaction allowances.