Price change since February 2020
Change in the Producer Price Index from February 2020 (just before the pandemic) to August 2026:
Year-by-year changes
For concrete, cement and brick, most of the increase came in 2022 and 2023. Ready-mixed concrete rose more than 10% in both years and cement nearly as much. Both slowed to under 2% in 2025.
| Material | 2021 | 2022 | 2023 | 2024 | 2025 | Feb 2020 to Aug 2026 |
|---|---|---|---|---|---|---|
| Steel mill products | +90.3% | +8.7% | −16.2% | −8.8% | +2.4% | +107.4% |
| Construction sand, gravel and crushed stone | +4.0% | +10.1% | +9.9% | +7.5% | +7.0% | +56.1% |
| Gypsum products (drywall) | +18.1% | +19.9% | +4.0% | +3.0% | +1.7% | +51.8% |
| Ready-mixed concrete | +3.8% | +10.3% | +11.1% | +5.8% | +0.8% | +39.0% |
| Cement | +4.0% | +9.6% | +12.2% | +5.9% | +1.6% | +38.7% |
| Lumber and plywood | +41.1% | −0.8% | −23.1% | −1.7% | +3.4% | +35.7% |
| Brick and structural clay tile | +4.7% | +9.3% | +7.4% | +4.6% | +1.9% | +34.5% |
| Asphalt paving mixtures and blocks | +3.6% | +16.7% | +4.5% | +2.5% | +2.9% | +28.5% |
Lumber is the exception: it jumped 41% in 2021, then fell back in 2023. Steel followed the same pattern on a larger scale.
What this means for a project budget
These indexes track what producers charge, not the final retail price, but they move in the same direction. As a rough guide, a concrete order that cost $1,000 in early 2020 would cost about $1,390 for the same concrete today, and $1,000 of gravel would cost about $1,561.
- Re-price old estimates. A quote or budget from 2021 or earlier is likely 30–50% low for concrete, gravel and drywall.
- Measure carefully. With materials costing more, over-ordering costs more too. The concrete calculator and gravel calculator give exact quantities with a waste allowance.
- Compare bagged and ready-mix. The concrete cost calculator prices a slab both ways with your local prices. See also how much a yard of concrete costs.
About the data
The Producer Price Index (PPI) measures the average change in prices that domestic producers receive for their output. It is published monthly by the U.S. Bureau of Labor Statistics. The figures above use these BLS series: ready-mixed concrete (WPU1333), cement (WPU1322), construction sand, gravel and crushed stone (WPU1321), asphalt paving mixtures and blocks (WPU1394), lumber and plywood (WPUSI004011), gypsum building materials (WPU13710102), brick and structural clay tile (WPU1342) and steel mill products (WPU1017).
The year-by-year and cumulative changes are taken from the AGC's PPI tables (updated October 15, 2026). They are national figures; local prices can rise faster or slower depending on supply and distance from plants and quarries. For ready-mix concrete by region, see concrete price changes by region since 2020.
Using these numbers
You're welcome to use the chart and table in articles, reports or class materials. Please credit Free Construction Calculators with a link to this page, and cite the BLS as the original data source. We update this page when new annual data is released.