How to calculate a concrete mix
- Find the wet volume of concrete you need: length × width × thickness, in cubic feet. Divide by 27 for cubic yards.
- Multiply by 1.54 for the dry volume. Sand, gravel and cement contain air gaps that disappear when they are mixed with water, so it takes about 54% more loose material than finished concrete.
- Split the dry volume by the ratio. For 1 : 2 : 3 there are 6 parts: cement is 1/6, sand 2/6 and gravel 3/6.
- Convert to bags and tons. A 94 lb bag of portland cement is about 1 cu ft. Sand and gravel are sold by the cubic yard or ton.
- Add water by the water-cement ratio: 0.5 means 0.5 lb of water per lb of cement. Less water makes stronger concrete; more makes it easier to place but weaker.
Concrete mix formula
Cement (cu ft) = dry volume × cement parts ÷ total parts · Bags = cement cu ft (1 bag ≈ 1 cu ft)
Water (lb) = cement lb × water-cement ratio · Gallons = lb ÷ 8.34
Worked example: one cubic yard of 1 : 2 : 3
1 cu yd is 27 cu ft wet, or 41.6 cu ft dry. Cement is 41.6 ÷ 6 = 6.9 cu ft, so about 7 bags of 94 lb portland cement. Sand is 13.9 cu ft (0.51 cu yd) and gravel 20.8 cu ft (0.77 cu yd). At a 0.5 water-cement ratio, add about 39 gallons of water.
Mix ratio chart per cubic yard
Materials for 1 cu yd of finished concrete, before waste, at a 0.5 water-cement ratio:
| Ratio | Cement bags (94 lb) | Sand (cu yd) | Gravel (cu yd) | Water (gal) | Typical use |
|---|---|---|---|---|---|
| 1 : 1.5 : 3 | 8 (7.6) | 0.42 | 0.84 | 43 | Rich: suits thin sections and work that needs extra strength |
| 1 : 2 : 3 | 7 (6.9) | 0.51 | 0.77 | 39 | Strong general mix: slabs, footings, steps |
| 1 : 2 : 4 | 6 (5.9) | 0.44 | 0.88 | 33 | Standard general-purpose mix: paths, patios, bases |
| 1 : 3 : 6 | 5 (4.2) | 0.46 | 0.92 | 23 | Lean mix: blinding layers, mass fill, non-structural |
Volume ratios give an estimate. Strength depends on the cement, the aggregates, the water you add and curing, so for structural work order ready-mix to a specified strength instead of mixing by ratio.
Mixing from scratch vs bagged concrete
Pre-mixed bags already contain cement, sand and gravel, so you only add water. They cost more per yard but are simpler for small jobs: see the concrete bag calculator. Mixing your own from portland cement, sand and gravel is cheaper once you need more than about half a yard, and for a yard or more a ready-mix delivery is often cheapest of all. Use the concrete calculator first to find the volume.
Mixing tips
- Measure parts with the same bucket or shovel count every batch so the mix stays consistent.
- Mix the dry materials first, then add water gradually. The mix should hold its shape without being soupy.
- Use clean, well-graded sand and gravel. Order them with the sand calculator and gravel calculator.
- Keep fresh concrete damp for the first week so it cures properly.
Frequently asked questions
How many bags of cement are in a yard of concrete?
For a 1 : 2 : 3 mix, about 7 bags of 94 lb portland cement per cubic yard. Richer mixes use more and lean mixes less.
What is the best concrete mix ratio?
1 : 2 : 3 (cement : sand : gravel) is a strong all-round mix for slabs and footings. 1 : 2 : 4 is a standard general-purpose mix, and 1 : 3 : 6 a lean mix for non-structural fill.
Why multiply by 1.54 for dry volume?
Loose cement, sand and gravel have air gaps. When mixed with water the fine particles fill the gaps between the coarse ones, so the finished volume is smaller. 1.54 is the usual allowance.
How much water do I add to a concrete mix?
Use a water-cement ratio of about 0.45 to 0.55 by weight. For one 94 lb bag of cement at 0.5, that is 47 lb, or about 5.6 gallons of water.
How much sand and gravel per bag of cement?
For a 1 : 2 : 3 mix, each bag of cement goes with about 2 cu ft of sand and 3 cu ft of gravel.
Sources & standards
This calculator's formulas and default values are based on the following codes, standards and published data. Codes are adopted and amended locally, so check with your building department for permitted work. See how we build and check our calculators.
- Portland Cement Association (PCA), Design and Control of Concrete Mixtures: water-cement ratio, materials and proportioning.
- ASTM C150 Standard Specification for Portland Cement: standard 94 lb bag, about 1 cu ft.
- Common site-batching practice: dry-volume factor of about 1.54 for nominal volume mixes.