How Many Yards of Concrete Are in a Truck? Capacity, Weight and Loads

Ordering ready-mix starts with one question: how much does a truck carry? This guide covers standard truck sizes, why the drum is never full, how many trucks your slab needs, how much a loaded truck weighs and how long you have to place the concrete.

Quick answer

A standard ready-mix concrete truck carries about 8 to 10 cubic yards, and 10 yards is the most common full load. Some larger trucks haul 11–12 yards, while tow-behind mixing trailers carry about 1–1.75 yards. A full 10-yard load of normal concrete weighs about 40,500 lb (just over 20 tons) before you count the truck.

Bar chart of concrete load weight by truck load, from 4,050 pounds for 1 cubic yard to 40,500 pounds for a full 10 cubic yard truck
Weight of the concrete alone at 4,050 lb per cubic yard. A standard truck carries 8–10 yards.

How much concrete a truck holds

Mixer trucks are sold by drum size, but what a truck can legally and safely carry is less than the drum's full volume. Concrete has to tumble to stay mixed, so the drum is never filled to the top. Road weight limits cap the load too.

Typical ready-mix trucks use drums rated about 9–12 cubic yards, with the size held down by the gross weight of the loaded truck (Pavement Interactive). In day-to-day ordering that works out to:

Truck typeTypical loadGood for
Tow-behind mixing trailerAbout 1–1.75 cu ydFence posts, small pads, steps
Partial load on a standard truckAny amount up to the truck's capacityPatios, walkways, small slabs (often with a short-load fee)
Standard rear-discharge mixerAbout 8–10 cu ydGarage floors, driveways, foundations
Large mixer (extra axles)About 11–12 cu ydBig slabs and commercial pours

Exact limits depend on the truck, its axle setup and your state's weight rules, so ask the plant what its trucks carry before you plan the pour.

Mixer rating vs agitator rating

A truck mixer usually carries two capacity ratings: one as a mixer and a higher one as an agitator (TxDOT Pavement Manual). When the concrete is mixed in the truck, the drum can be filled to 63% of its total volume. When the concrete was already mixed at a central plant and the truck only keeps it moving, the limit rises to 80% (Pavement Interactive, citing AASHTO).

Drum gross volumeAs a mixer (63%)As an agitator (80%)
12 cu yd7.6 cu yd9.6 cu yd
14 cu yd8.8 cu yd11.2 cu yd
16 cu yd10.1 cu yd12.8 cu yd
18 cu yd11.3 cu yd14.4 cu yd

That's why a "10-yard truck" has a drum much bigger than 10 cubic yards. For a homeowner, the number that matters is simply the load the plant will send, which for most trucks is 9 or 10 yards.

How many trucks do I need?

Work out the volume, add a margin, then divide by the truck load and round up. Here's the method step by step:

  1. Find the volume in cubic feet: length (ft) × width (ft) × thickness (in) ÷ 12.
  2. Convert to cubic yards: divide by 27.
  3. Add extra: 5–10% for uneven subgrade, form bulge and spillage. The concrete calculator uses 10% by default.
  4. Divide by the truck load (usually 10 yd) and round up to get the number of trucks. The last truck carries whatever is left.

Trucks needed for common slabs, with 10% extra and 10-yard trucks:

PourExact volumeWith 10% extraTrucks
Patio 10 × 10 ft, 4 in1.23 cu yd1.36 cu yd1 (short load)
Patio 12 × 16 ft, 4 in2.37 cu yd2.61 cu yd1 (short load)
One-car garage 12 × 20 ft, 4 in2.96 cu yd3.26 cu yd1
Two-car garage 24 × 24 ft, 4 in7.11 cu yd7.82 cu yd1
Driveway 12 × 50 ft, 5 in9.26 cu yd10.19 cu yd1–2 (see below)
Basement floor 30 × 40 ft, 4 in14.81 cu yd16.30 cu yd2
Shop slab 40 × 60 ft, 6 in44.44 cu yd48.89 cu yd5

Worked example: a 12 × 50 ft driveway at 5 in thick is 12 × 50 × 5 ÷ 12 = 250 cu ft, and 250 ÷ 27 = 9.26 cu yd. With 10% extra that's 10.19 cu yd, just over one 10-yard load. You have three choices: ask whether the plant's trucks can carry 10.5 yards, trim the margin to about 8% (10.0 yd) if your subgrade is flat and well compacted, or order a second small load. A second truck for 0.2 yd usually means a short-load fee, so talk it through with the dispatcher before the pour.

For big pours, ask the plant to space the trucks so the next one arrives as the last one empties. Gaps between loads can leave cold joints where fresh concrete meets concrete that has started to set.

How much does a concrete truck weigh?

Normal-weight concrete is about 150 lb per cubic foot, or 4,050 lb per cubic yard (the same figure our concrete weight calculator uses). The load alone gets heavy fast:

1 cu yd4,050 lb
3 cu yd12,150 lb
5 cu yd20,250 lb
8 cu yd32,400 lb
10 cu yd40,500 lb
12 cu yd48,600 lb
LoadConcrete weightTons
1 cu yd4,050 lb2.0
3 cu yd12,150 lb6.1
5 cu yd20,250 lb10.1
8 cu yd32,400 lb16.2
10 cu yd40,500 lb20.3
12 cu yd48,600 lb24.3

An empty mixer truck weighs roughly 20,000–30,000 lb (Wikipedia), so a truck with a full 10-yard load comes to about 60,500–70,500 lb. On the Interstate system the federal limit is 80,000 lb gross, 20,000 lb on a single axle and 34,000 lb on a tandem axle (23 CFR 658.17), and states set their own rules on other roads. Axle limits like these are why trucks rarely carry more than 10–12 yards.

Protect your property

A loaded mixer can crack an existing driveway or sidewalk, sink into soft lawn and crush septic tanks, drain fields and buried lines. Plan where the truck will park and how the concrete will reach the forms. If the chute can't reach, budget for a pump or wheelbarrow crew.

How long concrete can stay in the truck

Water starts the cement reacting as soon as the truck is loaded, so there's a clock on every load. The ready-mix standard, ASTM C94, calls for discharge to be completed within 1½ hours or before the drum has turned 300 revolutions after water is added, whichever comes first, unless the buyer agrees otherwise. Hot weather shortens the working time. Have forms, rebar, tools and helpers ready before the truck arrives, and don't let the driver add extra water to make it easier to place: it weakens the concrete.

Small pours: short loads and bags

Many plants have a minimum order and add a short-load fee for small loads, which is why a 1-yard order can cost far more per yard than a full truck. See short-load fees and concrete cost per yard for typical prices, or price your own job with the concrete cost calculator.

Under about a yard, bags are often the easier choice. One cubic yard takes 45 bags of 80 lb mix (0.60 cu ft each) or 60 bags of 60 lb mix (0.45 cu ft each). Our guide to how many bags of concrete you need has a full chart.

Common mistakes

  • Ordering the exact volume. Subgrade is never perfectly flat. Running out mid-pour costs much more than a little extra.
  • Forgetting the thickness is in inches. Divide inches by 12 before multiplying, or your volume is 12 times too big.
  • Assuming every truck carries 10 yards. Ask the plant for its actual load size and plan your truck count around it.
  • Leaving long gaps between trucks. Schedule loads back to back on big pours to avoid cold joints.
  • Not planning truck access. Check for overhead wires, soft ground, septic systems and how far the chute will reach.

Frequently asked questions

How many yards of concrete are in a truck?

A standard ready-mix truck carries about 8 to 10 cubic yards, and 10 yards is the most common full load. Larger trucks can haul 11–12 yards, and tow-behind mixing trailers carry about 1–1.75 yards.

How many yards does a concrete truck hold when it's full?

Most full loads are 9 or 10 cubic yards. The drum itself is bigger: it can only be filled to 63% of its volume when mixing, or 80% when carrying concrete that was mixed at the plant.

How much does a full concrete truck weigh?

A 10-yard load of normal concrete weighs about 40,500 lb. Add an empty truck of roughly 20,000–30,000 lb and a full truck weighs about 60,500–70,500 lb.

How many concrete trucks do I need?

Divide your volume in cubic yards (with 5–10% extra) by the truck load, usually 10 yards, and round up. A 24 × 24 ft garage floor at 4 in needs about 7.8 yd, so one truck; a 30 × 40 ft basement floor needs about 16.3 yd, so two.

How long can concrete stay in the truck?

ASTM C94 calls for the load to be discharged within 1½ hours or 300 drum revolutions after water is added, whichever comes first, unless the buyer agrees otherwise. Hot weather shortens the working time.

Can I order less than a full truck of concrete?

Yes. Plants deliver partial loads, but many charge a short-load fee below a minimum order. For less than about a yard, 80 lb bags (45 per cubic yard) are often cheaper.

Sources

Published November 27, 2026. This guide is general information. Load sizes and weight limits vary by supplier and state, so confirm with your ready-mix plant before ordering.